Tuesday, December 17, 2019

THE CITIZENS AGAINST THE CROTON POINT AVENUE PROJECT FB PAGE HAS AN UPDATE---THE NEW BIDS ARE IN

December, 2019 update: Three bids were submitted. The lowest came in at $3.8 million. This number is $1 million higher than anticipated.

Additionally, project management costs came in at $747K; $147K higher than anticipated.


At a recent Village Board work session, the Village Manager anticipated borrowing $1.9 million to complete this project.


At the December 16th meeting, that number is now $3 million, as per the Village Manager.  https://www.facebook.com/stoptheCPAproject/


AND A 12/20 UPDATE https://everythingcroton.blogspot.com/2019/12/on-croton-point-avenue-fiasco-this.html

6 comments:

  1. WHO WAS THE LOWEST BIDDER AT 3.8M?

    ReplyDelete
  2. Build it no matter what the cost! There's bicyclists and walkers and champs d'elysee! Insanity!

    ReplyDelete
  3. It's not a government contract unless it has a minimum of 6 zeros!

    ReplyDelete
  4. The entire board recently voted to go ahead with this.

    ReplyDelete